How to calculate percent complete on a pay application

Work out percent complete for each line of a schedule of values from work completed, stored materials and the scheduled value, with a worked example.

What percent complete means

Percent complete is the share of a schedule of values line that has been completed and stored to date. It tells the owner how much of each item is billed, and the balance to finish is built from the same figure.

On a pay application, every line needs its own percent complete. The totals at the bottom only make sense if each line is right first.

Percent complete is never a guess about how the work looks. It is the completed and stored amount divided by the scheduled value, and the owner can check it against the schedule of values line by line.

The formula

For each line, add the work completed to date to the materials stored to date. Divide that total by the scheduled value for the line, then multiply by 100.

Percent complete = (work completed to date + materials stored to date) divided by the scheduled value, times 100.

The earned amount on the application is the sum of each line's completed and stored amount. The balance to finish on each line is the scheduled value minus that amount.

A worked example

Take one line of a schedule of values, for a drywall package:

  • Scheduled value for the line: 200,000.
  • Work completed in earlier applications: 60,000. Work completed this period: 30,000.
  • Materials stored on site, not yet installed: 10,000.
  • Total completed and stored to date: 60,000 plus 30,000 plus 10,000, which is 100,000.
  • Percent complete: 100,000 divided by 200,000, which is 50 percent.
  • Balance to finish on the line: 200,000 minus 100,000, which is 100,000.

Check the result before you send it

The line reads 50 percent complete, with 100,000 still to finish. Retainage is applied to the 100,000 completed and stored to date, not to the scheduled value. You can check your own numbers with our free pay application calculator.

Compare each line with the site. If a line says 90 percent but the work is visibly half done, the number is wrong, not the site. Check stored materials against the delivery tickets, and check change order lines against the approved paperwork.

Before you trust the spreadsheet or the software, do one line by hand. Recalculate it with the formula above and compare the result with the figure on the application. If they match, the set-up is right, and the other lines can be checked the same way.

Common mistakes

Most percent complete errors come from the inputs, not the division. Watch for these:

  • Counting stored materials twice, once in the stored column and again in this period's work.
  • Leaving approved change orders out of the base. An approved change order belongs in the scheduled value or in its own line, so the percent complete uses the right base.
  • Using the original contract sum after change orders are approved, which makes every line look less complete than it is.
  • Billing above 100 percent on a line. A line cannot be more than fully complete without a change order.

Keep the scheduled values right

Percent complete is simple arithmetic, so most errors start with the scheduled values. Make sure the lines add up to the contract sum, that each line has one clear scope, and that approved changes are recorded before the next application is prepared.

Watch for lines that carry both an original scope and an approved change. Splitting them into separate lines keeps the percent complete for the original work clear, and it makes the change order easy to trace later.

Get the scheduled values and the stored amounts right, and the rest follows from the formula.