RFI vs. change order: when to use which

An RFI asks a question about the contract documents. A change order changes the contract. Here is how to tell which one you need.

Short answer

Use an RFI when you need a clear answer about the contract documents, such as what a detail means or which specification governs. Use a change order when the answer changes the scope, cost or time of the contract.

Both can come up on the same issue. An RFI often comes first, and its answer may show that the work changes. In DrawOx they are separate records, so each keeps its own history and status.

Examples of each

An RFI example: the drawings show one wall type, but the specification lists another for the same location. The contractor asks which one governs before building the wall.

A change order example: the owner asks for a door that is not in the contract. The added work, its cost and any extra days are written up so the owner can approve them.

What happens when an answer changes the work

An answer to an RFI does not change the contract by itself. If the answer adds or removes work, the change still has to be recorded on a change order.

DrawOx can draft a change order from an RFI. Open the RFI, make sure it has an official response, and use the "Create change order from this RFI" action. The app then asks an AI step to list the work items the response implies, prices them, and saves a draft change order linked to the RFI.

The AI step lists only items the RFI text supports. If the text gives no basis for a quantity, it returns no items. The app then uses the cost entered on the RFI, or creates a draft that needs pricing.

Only one change order is created per RFI. A second click returns the change order that already exists.

How DrawOx tracks each

RFIs live in the RFI log, from draft through closed. Change orders live in the Change Orders list under the Financials Hub.

An owner change order moves from draft to pending in review. From there it can be approved, rejected or voided, and while it is under review it can also be marked revised or not proceeding.

Only an owner or admin can approve, reject or void a change order. A change order total is the sum of its line amounts.

What a change order records

Each change order has a number and a title, and a list of line items. Every line has a description, an optional cost code and an amount, and the change order total is the sum of those amounts.

A change order can also carry notes, attachments and the number of schedule days the change adds. Every status change is written to its history with the name of the person who made it and the time.

Because the history is kept, a change order can show who submitted it, who asked for a revision and who approved it, which is the record a dispute usually needs.

A quick test before you choose

  • Is someone asking what the documents mean? Use an RFI.
  • Does the answer change the price, the schedule or the scope? Use a change order once the answer is final.
  • Is the extra work agreed in principle but not yet priced? Track it on a change order so the cost is on record.

Keep the two records linked

Note the RFI number on the change order and the change order on the RFI. Anyone who opens either record can then see where the change came from.