Change orders: the money you never billed

How unapproved changes turn into lost money, and how to track each change order from request to approved total.

Short answer

A change order records a change to scope, cost or time. It counts toward the contract only once it is approved, so a change that is never recorded is money you may never bill.

In DrawOx, each change order moves through set statuses. Only approved owner change orders are counted in the approved total and added to pay applications.

Why unbilled changes happen

  • Work starts before the change is agreed.
  • An approval is given by phone or in the field, and nothing is written down.
  • The request is logged late, so the cost and the date are hard to prove.

What a change order records

Each change order has a number and a title, and a list of line items. Every line has a description, an optional cost code and an amount, and the total is the sum of those amounts.

An owner change order can also carry notes, attachments and the number of schedule days the change adds. Every status change is written to its history with the name of the person and the time.

The statuses and how they move

An owner change order has seven statuses: Draft, Pending – In Review, Pending – Revised, Pending – Not Proceeding, Approved, Rejected and Void.

A draft is submitted for review, and it needs line items to be submitted. From In Review it can be approved, rejected, voided, marked revised or marked not proceeding. A revised change order can be resubmitted for review, approved, rejected or voided. An approved change order can be reverted to pending, with a reason.

A change order can be edited while it is a draft or pending. Once it is approved, rejected or void, it is read-only.

Change orders that start as an RFI

A change order often starts with an RFI. On an RFI with an official response, the "Create change order from this RFI" action drafts a change order linked to that RFI. Only one change order is created per RFI.

Subcontractor change orders are tracked too. They have five statuses: Draft, Pending – In Review, Approved, Rejected and Void.

Who can approve, reject or void

Only an owner or admin can approve, reject or void a change order. Other roles cannot make those three decisions.

Seeing the totals

The Financials Hub has a Change Orders card with two numbers: Pending Changes and Approved Changes.

Approved Changes adds up the approved owner change orders. Pending Changes adds up the owner change orders that are Pending – In Review or Pending – Revised. Draft, Rejected, Void and Pending – Not Proceeding change orders are not counted in either number.

How approved change orders reach pay applications

When you create a pay application, the approved owner change orders are added to it as lines, each marked as a change order line with its amount as the scheduled value.

If a change order is approved after the application was created, the application shows a note that approved change orders are not on it yet. A draft application can add them, and only the approved change orders that are missing are added.

An application that is under review is not changed, and neither is one that has been certified. Add change orders before you submit.

A practical habit

Write the change order before the work starts, and log the request the same day. A short entry made at the time is worth more than a long one rebuilt later.