How to build a G702/G703 pay application from your schedule of values
Build a G702/G703-style pay application from your schedule of values, with the steps to check before it goes to the owner.
Short answer
A pay application shows the work billed to date, the retainage held back, and the payment due for the period. In DrawOx, set up the schedule of values on the contract, enter each line's work for the period, check the totals, get the application approved, then certify and export it.
The output is a G702/G703-style summary. It follows the layout of the standard G702 and G703 forms, but it is not the official AIA form. Review it before you send it to the owner. You can check this with our free pay application calculator.
Step 1: set up the schedule of values
The prime contract holds the schedule of values: one line for each item, each with an item number and a scheduled value. Item numbers must be unique.
The contract also holds the retainage rate. Each new pay application takes that rate from the contract.
The contract can be edited while it is in draft or out for signature. Once it is approved, it is locked.
Step 2: enter this period's work
Create the application for the billing period. A period takes one pay application.
For each line, enter the work done this period and any materials stored. If retainage is being released on a line, enter that amount too. Negative amounts are set to zero.
Only a draft, or an application sent back for revision, can be edited.
Step 3: check the totals
The app calculates these figures for each application:
- Completed and stored to date, per line: previous work, plus this period's work, plus stored materials.
- Balance to finish, per line: scheduled value minus completed and stored.
- Retainage: the retainage carried forward from the last approved application, plus the rate times this period's work and stored materials, minus the amount released.
- Earned less retainage: total completed and stored, minus retainage.
- Current payment due: earned less retainage, minus payments on earlier applications.
- Balance due: current payment due, minus payments recorded on this application.
How retainage carries forward
Each line's retainage is its completed-and-stored amount times the application's rate. Retainage carries forward only from applications that have been approved, so an unapproved application does not change the next one.
Step 4: approve, certify and lock
Submit the application for review. The reviewer either approves it or returns it for revision, and a return needs a comment.
Only an approved application can be certified. Certification needs the certifier's name, title, date and a typed signature, and it is final once saved.
Only an owner or admin can certify an application, lock a billing period or reopen one. Locking a period needs a reason. A locked period takes no new applications and no new payments until it is reopened.
Step 5: export
The G702/G703-style PDF is made for one application. Its summary page carries the G702 figures, including the contract sum, change orders, completed and stored, retainage, earned less retainage and the payment due.
The continuation sheet has one row for each line item, with columns A to J and a totals row. Column J is retainage before releases, and the sheet shows the releases as a separate figure so the totals tie to the summary.
The Excel export is a different file. It lists every pay application in one workbook, one row per application, with the money columns and a Total row. It does not show line items.
Before you send it
- Check that every line's scheduled value matches the contract.
- Check the retainage rate on the application.
- Check the certifier's details, because certification is final.
Send a clean package
Once applications are going out, read how to track owner pay applications to follow each one through payment.