How to track owner pay applications
Track every owner pay application across billing periods: what to record, how statuses move, how retainage carries forward, and a month-end routine.
TL;DR
To track owner pay applications, keep one record per billing period with the amount billed, the retainage held, the approval and certification status, the payments received and the balance still due. Review it at every month end.
This guide covers the figures to track, how an application moves from draft to certified, and a month-end routine that catches problems before the owner does. It focuses on tracking. For building the application itself, see how to build a G702/G703 pay application.
What an owner pay application is
An owner pay application is the contractor's request for payment for one billing period. It shows the work completed, materials stored, retainage and the amount due. The owner reviews it, and the architect or owner's representative may certify it before payment.
Each application builds on the last. The figures from earlier periods feed the new one, which is why a single bad application can throw off every one after it.
What to track for every application
Keep these fields for each billing period, whether you use a spreadsheet or software.
| Field | Why it matters |
|---|---|
| Billing period and application number | Keeps the sequence clear and prevents duplicates |
| Work completed this period | The amount you are asking to be paid for |
| Stored materials | Billed but not yet installed; must match delivery records |
| Retainage held and released | Affects cash flow and the final payment |
| Approved change orders included | Confirms the contract changes reached billing |
| Status and decision history | Shows who approved, returned or certified it |
| Payments received | Drives the balance due |
| Lien waiver status | Many owners hold payment without one |
How an application moves through its statuses
In DrawOx, an application starts as a draft that you can edit. You submit it for review. The reviewer approves it or returns it for revision, and a return needs a comment explaining why.
Only an approved application can be certified. Certification records the certifier's name, title, date and a typed signature, and it is final once saved. Only an owner or admin can certify an application or lock a billing period.
You can follow the same stages in a spreadsheet. Add a status column with draft, submitted, returned, approved and certified, plus a date for each change. The point is that nobody has to remember where an application stands.
Follow the retainage
Retainage is the money held back until the work is done. It builds up across applications, so you need to track it from period to period.
On each application, the retainage held equals the retainage carried forward, plus the rate times this period's work and stored materials, minus any amount released. DrawOx carries retainage forward only from approved applications, so a draft does not change the starting point for the next one.
Read retainage explained for the full formula and the mistakes to avoid.
A month-end routine
Run through this list at the end of each billing period. It takes about the same time whether you have one job or ten.
- Confirm the last application was approved and, if required, certified.
- Check that every approved change order is on the new application.
- Compare stored materials to delivery tickets.
- Enter this period's work on each line and recheck percent complete.
- Confirm the retainage carried forward matches the last approved application.
- Test one line by hand against the totals.
- Collect the lien waiver your owner expects with the payment.
- Submit the application and write down the date.
Track payments against each application
Billing is not the same as getting paid. Record each payment against the application it pays, with the date and amount. The balance due on an application is the current payment due minus the payments recorded on it.
Look at the open balances every week. An application that was approved a month ago and still shows a balance is a call you should be making.
Subcontractor invoices belong in the same picture
If you are a general contractor, your owner application is built partly on what your subs bill you. DrawOx keeps subcontractor invoices in the same area as owner applications, so both sides of the billing sit in one place.
Reconcile the two each period. If a subcontractor bills more than the schedule of values allows, you want to find out before your own application goes out.
Spreadsheet or software for tracking
| Question | Spreadsheet | Software |
|---|---|---|
| One job, one person | Works well | More than you need |
| Several jobs | Hard to keep consistent | One place for all |
| Retainage carry-forward | Easy to break with one edit | Calculated from approved applications |
| Approval history | Typed by hand | Recorded with name and time |
| Change orders on the application | Retyped | Approved ones added as lines |
Common mistakes
- Billing before the change order is approved.
- Carrying retainage from a draft application.
- Forgetting stored materials from last period when you calculate percent complete.
- Not recording payments, so no one knows the open balance.
- Locking a period before every payment is entered.
A worked example across two periods
These numbers are an illustration with a 10 percent retainage rate. Take one schedule of values line worth 500,000.
| Figure | Period 1 | Period 2 |
|---|---|---|
| Work this period | 100,000 | 150,000 |
| Completed and stored to date | 100,000 | 250,000 |
| Retainage held | 10,000 | 25,000 |
| Earned less retainage | 90,000 | 225,000 |
| Payments on earlier applications | 0 | 90,000 |
| Current payment due | 90,000 | 135,000 |
Read the example
In period 2, retainage is the 10,000 carried forward plus 10 percent of 150,000, which is 15,000. That makes 25,000. Earned less retainage is 250,000 minus 25,000, or 225,000. Subtract the 90,000 already certified and the payment due is 135,000.
If your tracker does not reproduce numbers like these, something upstream is wrong. Try the same figures in our free pay application calculator.
Why applications get returned
Knowing the usual reasons lets you check for them before you submit.
- The scheduled values do not match the contract.
- A line is billed above 100 percent complete.
- Stored materials have no delivery support.
- An approved change order is missing, or an unapproved one is included.
- Retainage does not match the last approved application.
- The required lien waiver or backup is not attached.
- The period dates or application number are wrong.
Forecast cash from your tracker
Once you track each application, you can see cash coming. Add the current payment due on every submitted application, then subtract what has arrived. The remainder is what you expect.
Retainage is the part that arrives last. Total the retainage held across jobs so the number does not surprise you at the end of the year. Plan around it the same way you plan around payroll.
Close out the final application
The last application releases retainage and closes the contract value. Before you send it, confirm that punch list items are closed, final lien waivers are in, and every approved change order is billed.
The punch list guide explains why closeout depends on that list. Lock the billing period only after every payment is recorded.
Frequently asked questions
How often should I submit an owner pay application?
Follow the billing period in your contract, which is usually monthly. Missing the cutoff can delay payment by a full period, so put the date on your calendar at the start of the job.
What is the difference between approved and certified?
Approved means the reviewer accepted the application. Certified means a named person signed it as final. In DrawOx an application must be approved before it can be certified, and only an owner or admin can certify.
What should I do if the owner returns the application?
Read the comment, correct the lines it names, and resubmit. An application that has been sent back for revision can be edited again.
Should retainage come from the whole contract or each application?
Check your contract. In DrawOx the rate is set once on the prime contract and applied to the work and stored materials billed on each application, with earlier retainage carried forward.
Can I track pay applications in Excel?
Yes, if you keep the fields above and protect your formulas. For several jobs or frequent change orders, a tool that links change orders and retainage reduces errors.