How to track RFIs from open to closed on a construction job

Learn how an RFI moves from draft to open, answered and closed in DrawOx, who holds it at each step, and how to find overdue requests.

Track an RFI from save to close

To track an RFI from open to closed in DrawOx, save it, send it to the people who must respond, watch its status and the ball-in-court line, and close it once the answer is final.

An RFI, or request for information, is how a contractor asks the design team or owner to clarify something in the contract documents before work continues. Until the RFI is closed, someone on the job should always know who holds it and what happens next.

Each step below describes what the app does with one RFI, from the first save to the final close. The same steps apply to every RFI on a project, so the team can rely on the same record each time.

The four statuses

Every RFI moves through four statuses. The status tells you whether the RFI is still with the team, waiting on someone, or finished.

  • Draft: saved but not sent. If the email fails, the RFI stays a draft.
  • Open: sent, and at least one required assignee has not responded yet.
  • Answered: every required assignee has responded.
  • Closed: the RFI creator or an admin has closed it. A closed RFI no longer accepts responses.

Assign who must respond

Each assignee is emailed their own response link. A required assignee holds the ball in court until they respond. Assignees who are not required, and people on the distribution list, do not change the status.

An answer from an optional assignee does not move the RFI to answered. Only the required assignees decide when the RFI is answered.

Before you save, decide which people must answer and mark them as required. The required flag is what makes an assignee responsible for the RFI, so it matters more than the order names are entered in.

Distribution list members can view the RFI read-only. A private RFI stays hidden from them unless they are also an assignee.

Watch the ball-in-court line

The ball-in-court line names who is holding the RFI and shows how many required responses are in, for example "Name A (2 of 3 responded)". Use it to follow up with the right person.

The line lists only the required assignees who have not yet responded. When every required assignee has answered, the line is empty and the RFI moves to answered.

Find overdue RFIs

Open the Overdue view on the RFI list to see RFIs that are not closed and are past their due date.

The RFI list has four views: draft, open, closed and overdue. The open view includes answered RFIs, so an answered RFI stays in that view until it is closed.

An RFI without a due date cannot appear in the Overdue view, because the view checks the due date. Set a due date when you save the RFI, so it is included when the list is checked.

Close the RFI

Close the RFI from its record once the answer is final. Closing needs an official response, so mark the answer that governs as the official response before you close. The app refuses to close an RFI without one.

Only the RFI creator or an admin can close it. Closing clears the ball-in-court line and records "Closed RFI" in the RFI history.

Once an RFI is closed, it no longer accepts responses, so a late answer cannot be added to it. Confirm the official response is recorded before you close, and keep the closing step for the final answer only.