How to track RFIs without Excel
Replace your Excel RFI log with a tracker that shows who holds each RFI, what is overdue and which answer is official. Includes a free RFI log template.
TL;DR
An RFI log needs to answer three questions at a glance: who holds each RFI, which ones are overdue, and which answer is the official one. Excel can do this for one small job. It struggles when several people edit it and answers arrive by email.
This guide lists what an RFI record must hold, how to write an RFI that gets answered, and how to track every request to closure. It includes a free RFI log template for teams that stay on a spreadsheet.
Already tracking RFIs in DrawOx? Read how to track RFIs from open to closed for the in-app workflow.
Where an Excel RFI log falls short
- The answer is in someone's inbox, not in the log.
- Nothing warns you when an RFI passes its due date.
- Two people edit two copies and the status disagrees.
- The log does not say who is holding the RFI right now.
- There is no clear record of which response governs.
What every RFI record needs
- A unique RFI number that you never reuse.
- A short subject and the full question.
- The drawing and spec section it refers to.
- Who asked, and who must answer.
- The date submitted and the response due date.
- A status: draft, open, answered or closed.
- The official response, once there is one.
- The cost and schedule impact, if any.
Write an RFI that gets answered
A vague RFI wastes the design team's time and yours. Make each one easy to answer.
- Ask one question per RFI. Split a long list into separate requests.
- Cite the sheet and the spec section so the reviewer can find the conflict.
- Propose a solution. "We plan to build it this way unless you tell us otherwise" speeds the reply.
- Set a realistic due date that matches your contract.
- State the impact if the answer is late, in days or in cost.
Track each RFI through its life
An RFI moves through a few clear stages. Track the stage and the person who holds it.
| Status | Meaning | Your next move |
|---|---|---|
| Draft | Saved, not sent | Finish and send it |
| Open | Sent, waiting on at least one required person | Chase the named person |
| Answered | Everyone required has replied | Confirm the official response, then close |
| Closed | Finished | Check cost and schedule impact |
Chase by name, not by hope
Every open RFI should show who owes the next response. In DrawOx, the ball-in-court line names the required assignees who have not responded yet, for example "Name A (2 of 3 responded)". When everyone required has answered, the line clears and the RFI moves to answered.
Review the overdue list at the start of each week. An RFI with no due date will never show as overdue, so set a date every time. For more on this, read how to track RFIs from open to closed.
RFI, submittal or change order?
People mix these up. Use the table below to pick the right record.
An RFI answer can lead to a change order. Link the two records so the cost traces back to the question. See RFI versus change order.
| Record | Use it when | Example |
|---|---|---|
| RFI | You need the documents clarified | The drawing and spec show different wall types |
| Submittal | You need approval of a product or shop drawing | Door hardware data sheets |
| Change order | The scope, cost or time changes | The owner adds a door not in the contract |
How DrawOx tracks RFIs
DrawOx keeps RFIs in one place with a status and a due date. You assign who must respond and mark each person as required or not. Each person gets an emailed response link, so each answer ties to the person who gave it.
Closing an RFI needs an official response. Mark the answer that governs, then close. Only the RFI creator or an admin can close one. The RFI list has draft, open, closed and overdue views, and the Project Management Hub counts overdue RFIs.
DrawOx also has a Draft with AI option in beta that writes an RFI into editable fields. Nothing saves until you save it, and you should read every line first. When an RFI has an official response that adds work, you can create a draft change order from it.
Use the free RFI log template
If you stay on a spreadsheet, build in the safeguards. Our free RFI log (Excel) has 200 rows, days open, an automatic OVERDUE flag, and status and cost-impact dropdowns.
Update it the day a response arrives. Set the status to answered or closed, and the overdue flag clears. A one-sheet guide inside the file lists seven habits that keep a log honest.
A weekly RFI check
- Open the overdue list and chase each person by name.
- Check that every answered RFI has an official response.
- Close finished RFIs so the open list stays short.
- Look for answers that change cost or schedule and start a change order.
A sample RFI you can copy
Use this as a pattern. Replace the details with your own.
Subject: Conflict between wall type on A-301 and Section 09 21 16. Question: Sheet A-301 shows wall type W4 at grid C, level 2. Section 09 21 16 calls for a different board thickness at the same location. Which one governs? Proposed solution: We plan to build to the sheet unless you tell us otherwise. Impact: Framing at this wall starts on the 14th. Response needed by the 10th to avoid standby time.
Notice what the example does. It cites the sheet and the section, asks one question, offers a solution and names the date that matters. A reviewer can answer it in a few minutes.
What to do when RFIs stall
Late answers are the normal problem, not the exception. Plan how you will chase before you need to.
- Follow up on the due date, by name, with the RFI number in the subject line.
- Call the person if the written reminder gets no answer. Then write down the call.
- State the schedule impact in the follow-up, in days.
- Raise the RFI at the next coordination meeting and record it in the minutes.
- Check your contract for any deemed-response or notice provisions, and send formal notice if it requires it.
Watch cost and schedule impact
An RFI answer can quietly add work. If the response changes the scope, the cost or the time, do not just build it. Write it up as a change order and tell the owner.
Record the impact on the RFI itself, even when you are not sure. A note that says cost impact is likely, to be priced, is better than silence. It shows you raised the issue when you first saw it.
Roll out the log to the whole team
A log only works if everyone uses it. Decide a few rules and stick to them.
- Pick one person to own the log and the numbering.
- Route every RFI through the log, even the ones that start in a phone call.
- Update it the day anything changes.
- Tell your subs how to submit questions to you, so their questions do not skip the log.
- Review it at your weekly meeting, starting with overdue items.
Frequently asked questions
What is an RFI in construction?
An RFI, or request for information, is a written question sent to the design team or owner to clarify the contract documents before work continues.
How long should an RFI response take?
It depends on your contract. Many projects set a response window of a few days to a couple of weeks. Put the due date on every RFI so a late answer shows up as overdue.
Can I track RFIs in Excel?
Yes, on a small job with one editor. Add a status, a due date and a days-open calculation, and update it daily. The risk grows with more editors and with answers that live only in email.
Which answer is the official response?
The one the design team or owner marks as governing. Record it on the RFI itself. An answer that stays in email is easy to lose or dispute.
What is the difference between an RFI and a submittal?
An RFI asks a question about the documents. A submittal sends product data, shop drawings or samples for approval before you buy or install.