How to write an RFI: steps, example and checklist
Write an RFI that gets a fast, clear answer. Follow six steps, see a complete filled-in example with the response, and avoid the mistakes that cause delays.
TL;DR
To write a good RFI, ask one specific question, cite the drawing sheet and spec section, explain what you plan to do if nobody answers, and state the date you need a response and what it affects. Keep it factual and short enough to answer in a few minutes.
Most RFI guides give you a blank template. This one shows a complete RFI from question to official response, so you can see how every part works. To track RFIs after you send them, read how to track RFIs without Excel.
What an RFI is
An RFI, or request for information, is a written question sent to the design team or owner to clarify the contract documents. It becomes part of the project record, so write it as if a stranger will read it years from now.
Use an RFI when the documents conflict, leave something out, or are unclear. Do not use one to ask for a design change or to ask something the documents already answer. If an answer changes cost or time, you will also need a change order. See RFI versus change order.
What to prepare before you write
- Read the drawing and the spec section for the area in question.
- Check earlier RFIs, addenda and bulletins in case it was already answered.
- Take a photo or mark up a sheet if the issue is physical.
- Find the date the answer is needed, from the schedule.
- Decide your proposed solution before you write.
Six steps to a good RFI
- Give it a specific subject, such as "Conflict between wall type on A-301 and Section 09 21 16", not "Wall question".
- State the question in one or two sentences. One question per RFI.
- Cite the evidence: sheet numbers, detail numbers, spec sections and any earlier RFI.
- Propose a solution, so the reviewer can say yes or correct you.
- State the impact and the date you need an answer, in plain terms.
- Attach a markup or photo if it helps, and send it to the person who can decide.
A complete example, from question to response
This example is made up. It shows the whole record.
RFI 014. Subject: Conflict between wall type on A-301 and Section 09 21 16, Level 2 corridor, grid C.
Question: Sheet A-301, detail 4 shows wall type W4 with one layer of 5/8 inch board each side. Section 09 21 16, Part 3, calls for two layers at corridor walls. Which governs?
Proposed solution: We plan to build to the specification, with two layers, unless you direct otherwise.
Impact: Framing at this wall starts on the 14th. We need a response by the 10th to avoid standby time. A second layer adds material and labor, and we will submit a change order if it is a change to the contract.
Response: Two layers at corridor walls govern. Sheet A-301 will be revised in the next bulletin. Marked official by the architect on the 9th.
Why that example works
- The subject names the sheet, the section and the location.
- It asks one question the reviewer can answer in a sentence.
- It cites exact references, so nobody has to hunt.
- It proposes a solution and states the date that matters.
- It flags the cost question without assigning blame.
- The response is recorded as official, so the answer is on the record.
Mistakes that cause delays
- Vague questions such as "the plans are unclear".
- Several questions in one RFI, so the answer comes back half done.
- No drawing or spec reference.
- No due date, so the RFI is never overdue.
- Assigning blame in the wording.
- Starting work on the proposed solution before an answer arrives.
Writing an RFI in DrawOx
In DrawOx, an RFI holds a subject, the question, the spec section and drawing reference, the people who must respond, a due date and a distribution list. Mark each person who must answer as required. Each person gets an emailed link to respond.
A Draft with AI option, in beta, can write an RFI into editable fields. Nothing is saved until you save it, so read every line and fix any detail that is wrong. Spec Chat can also start an RFI from an answer and carry over its page citations.
Closing an RFI needs an official response. Mark the answer that governs, then close it. If the answer adds work, you can create a draft change order from the RFI. Read how to set up a construction RFI log and track RFIs from open to closed for the in-app workflow.
RFI checklist
- Subject names the sheet, section and location.
- One question only.
- References are exact.
- Solution is proposed.
- Due date and impact are stated.
- Photo or markup attached if needed.
- Sent to the right person.
- Logged with a number and a due date.
Write for the person answering
The reviewer reads dozens of RFIs. Make yours easy to answer without a site visit. Put the question in the first two lines, put references in a list, and keep opinions out.
Use neutral words. Say "the drawing and the specification differ" instead of "the designer made an error". A calm RFI gets a calm, faster answer.
Follow up the right way
- Check the due date and follow up on that day, by name.
- Repeat the RFI number and the question in your follow-up.
- State the schedule impact in days if the answer is late.
- Raise it at the next coordination meeting and write it into the minutes.
- Record the official response on the RFI the day it arrives.
Frequently asked questions
Who writes an RFI?
Usually the contractor or a subcontractor, often the project manager or superintendent. It goes to the architect, engineer or owner who can answer it.
How long should an RFI be?
As short as it can be while staying specific. A few sentences, exact references and a proposed solution is usually enough.
How long does an RFI response take?
It depends on the contract and the team. Many projects set a response window of a few days to a couple of weeks. Put a due date on every RFI so a late answer shows as overdue.
Can I start work before the RFI is answered?
You can proceed at your own risk. If you build on your proposal and the answer differs, you may redo the work at your cost. Check your contract and tell the owner what you plan to do.
What is the difference between an RFI and a submittal?
An RFI asks a question about the documents. A submittal sends product data, shop drawings or samples for approval.
Start a 24-hour free trial at drawox.online. No card needed.