AIA pay application: what it is and how it works
What an AIA pay application is, how the G702 and G703 work, a worked example with real numbers, and the mistakes that get applications returned.
TL;DR
An AIA pay application is the standard way a contractor asks an owner for a progress payment. It has two parts. The G702 is the summary, called the Application and Certificate for Payment. The G703 is the continuation sheet that lists every line of the schedule of values.
This guide explains each part, walks through the G702 lines with a worked example, and shows the cycle from cutoff date to payment. If you are choosing a tool instead, read AIA pay application alternatives compared.
What an AIA pay application is
A pay application is a request for payment for work done during a billing period. The American Institute of Architects publishes the forms most commercial projects use. People say "AIA billing" for the whole process.
The form carries an architect's certification. The contractor signs the application, the architect reviews it and certifies the amount, and the owner pays the certified amount. The official forms are AIA documents, so check the AIA's terms if you plan to use them.
The two forms
The totals on the G703 must match the figures on the G702. When they do not, the owner sends the application back.
| Form | Also called | What it shows |
|---|---|---|
| G702 | Application and Certificate for Payment | The totals: contract sum, changes, work completed, retainage and the payment due |
| G703 | Continuation Sheet | One row for each line of the schedule of values, with work from earlier periods, this period and stored materials |
The schedule of values
The schedule of values breaks the contract into lines, such as site work, concrete, framing and finishes. Each line has a scheduled value, and the lines add up to the contract sum.
You bill each line by percent complete or by quantity installed. A good schedule has lines small enough to measure, and no line so large that its percent complete becomes a guess. Read how to calculate percent complete for the formula.
The G702 lines, with a worked example
The G702 builds the payment due in nine steps. The numbers below are an illustration with a 10 percent retainage rate and a prior application that certified 270,000.
| Line | What it is | Example |
|---|---|---|
| 1 | Original contract sum | 1,000,000 |
| 2 | Net change by change orders | 50,000 |
| 3 | Contract sum to date (1 + 2) | 1,050,000 |
| 4 | Total completed and stored to date | 420,000 |
| 5 | Retainage (10 percent of line 4) | 42,000 |
| 6 | Total earned less retainage (4 - 5) | 378,000 |
| 7 | Less previous certificates for payment | 270,000 |
| 8 | Current payment due (6 - 7) | 108,000 |
| 9 | Balance to finish, including retainage (3 - 6) | 672,000 |
Read the example
The owner has agreed to pay 1,050,000 in total, after change orders. You have completed and stored 420,000 of that work. The owner holds 42,000 as retainage, so you have earned 378,000 net.
You have already been certified 270,000, so this application asks for 108,000. The balance to finish, counting the retainage still held, is 672,000. You can test your own figures in our free pay application calculator.
The billing cycle
- Cutoff date: the contract sets a date, often the end of the month. Work through that date is billable.
- Prepare: update percent complete on each line, add stored materials and approved change orders.
- Attach backup: lien waivers, stored material invoices and any payroll or compliance documents the contract asks for.
- Submit: send the signed application to the architect or owner by the contract deadline.
- Review and certify: the reviewer checks it against the work on site and certifies an amount.
- Payment: the owner pays the certified amount within the contract terms, less retainage.
Mistakes that get applications returned
- Scheduled values that do not match the contract.
- Billing a line above 100 percent complete.
- Counting stored materials twice.
- Leaving out an approved change order, or including one that is not approved.
- Retainage that does not match the last approved application.
- A G703 total that does not tie to the G702.
- Missing signature, notarization or lien waiver.
Official form or AIA-style?
Some contracts require the official AIA forms. Others accept an application laid out like them. Check your contract before you pick a method, and ask the owner if it is not clear.
DrawOx produces a G702/G703-style summary from your schedule of values, approved change orders and retainage rate. It follows the layout of the standard forms but is not the official AIA form, so review it against your own application before you send it. See how to build a G702/G703 pay application for the steps.
Where retainage and lien waivers fit
Retainage reduces every payment until the job closes. Read retainage explained for how it builds up. Owners often want a lien waiver with each payment, and lien waivers before each pay application explains how to collect them.
Stored materials and change orders
Two items cause most of the arguments. Stored materials are products you have paid for or ordered but not yet installed. Owners usually want proof, such as invoices or delivery tickets, and some contracts require them to be insured or stored on site.
Change orders belong in the contract sum only once they are approved. A pending change order is a request, not an amount you can bill. Add approved changes as their own lines on the schedule of values so the percent complete on the original work stays clear.
Quick glossary
- Scheduled value: the part of the contract price assigned to one line.
- Completed and stored to date: work done plus materials stored, across all periods.
- Retainage: the share of each payment the owner holds until the job closes.
- Certificate for payment: the reviewer's statement of the amount due.
- Balance to finish: what remains to be billed, counting retainage.
Frequently asked questions
What does AIA stand for in a pay application?
AIA is the American Institute of Architects, which publishes the standard G702 and G703 forms that many commercial contracts use for progress payments.
What is the difference between a G702 and a G703?
The G702 is the summary page that shows the contract totals, retainage and the payment due. The G703 is the continuation sheet that lists every line of the schedule of values. The G703 totals must match the G702.
Who signs and certifies an AIA pay application?
The contractor signs the application. The architect or owner's representative reviews it and certifies the amount to be paid. Your contract names who certifies.
How often do I submit a pay application?
Follow the billing period in your contract, which is usually monthly. Missing the cutoff can push payment to the next period.
Can I use a spreadsheet instead of the official form?
Only if your contract allows it. Many contracts accept an application laid out like the G702 and G703, but some require the official documents. Check the contract and ask the owner when it is unclear.